Tag Archive for Borssele Beta

Borssele Beta topside installed

The topside of the Borssele Beta offshore station was successfully installed on the jacket foundation yesterday in the wind zone Borssele III & IV. The 3,650 t topside left the fabrication site of HSM Offshore in Schiedam on 30 March. The installation was performed by Seaway Heavy Lifting, using the heavy lift vessel Seaway Strashnov.…

Borssele Beta topside on its way to construction site

This morning the topside for the offshore platform Borssele Beta finally left the HSM Offshore yard in Schiedam. It is now on its way to the Borssele III & IV and V wind farm site, some 22 km off the coast of Vlissingen. As reported earlier last week, the 700 MW Offshore High Voltage Substation…

Topside for OHVS Borssele Beta ready for transport

The topside for the offshore platform Borssele Beta is ready for transport at the HSM Offshore yard in Schiedam. TenneT reported that the platform will be leaving the yard on Sunday, 22 March 2020. The 700 MW Offshore High Voltage Substation will collect the power from the 77 MHI Vestas, type V164, 9.5 megawatt wind…

HSM Offshore: Building the heart of an offshore wind farm

In 2002, HSM Offshore built the offshore substation for the first offshore wind farm, the Danish Horns Rev 1. Almost 17 years and several wind farm generations later, the Dutch manufacturing company is still building offshore platforms for the wind energy industry. The latest being the Borssele Alpha and Beta platforms. You won the contracts…

Jacket Borssele Beta installation in progress

On May 14, Boskalis, by order of TenneT, started with the installation of the jacket for the Borssele Beta Offshore High Voltage Substation.  The jacket was built by HSM Offshore in Schiedam. The jacket weighs 2,900 metric tonnes and is 55 metre heigh. The jacket will be fixed to the seabed by 6 piles. HSM…