Borssele Beta topside installed

© TenneT/Remco van Liempd

The topside of the Borssele Beta offshore station was successfully installed on the jacket foundation yesterday in the wind zone Borssele III & IV.

The 3,650 t topside left the fabrication site of HSM Offshore in Schiedam on 30 March. The installation was performed by Seaway Heavy Lifting, using the heavy lift vessel Seaway Strashnov. The jacket foundation was already installed back in May 2019.

The 700 MW offshore station is to be ready on 1 September and will collect the power produced by the Borssele III & IV and V wind turbines.